Half Year Accounts
Released
Released
Announcement PDF
TEMPEST MINERALS LIMITED ACN 612 008 358
Phone: +61 8 9200 0435 Fax: +61 8 9380 6761 Address: Level 2, Suite 9 389 Oxford Street, Mount Hawthorn WA 6016
ACN 612 008 358
CONSOLIDATED FINANCIAL REPORT
FOR THE HALF-YEAR ENDED
31 DECEMBER 2025
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
2 | P a g e
Contents
Cautionary Statements ..................................................................................................................................................2
Corporate Information...................................................................................................................................................4
Directors’ Report .............................................................................................................................................................5
Auditor's Independence Declaration ……………………………………………………………………………………… 17
Consolidated Statement of Profit or Loss and Other Comprehensive Income.....................................................18
Consolidated Statement of Financial Position ..........................................................................................................19
Consolidated Statement of Changes in Equity.........................................................................................................20
Consolidated Statement of Cash Flows.....................................................................................................................21
Notes to the Financial Statements..............................................................................................................................22
Directors’ Declaration ..................................................................................................................................................29
Independent Auditor’s Review Report.......................................................................................................................30
Cautionary Statements
Forward-looking statements
This document may contain certain forward-looking statements. Such statements are only predictions, based
on certain assumptions and involve known and unknown risks, uncertainties and other factors, many of which
are beyond the company’s control. Actual events or results may differ materially from the events or results
expected or implied in any forward-looking statement.
The inclusion of such statements should not be regarded as a representation, warranty or prediction with
respect to the accuracy of the underlying assumptions or that any forward-looking statements will be or are
likely to be fulfilled.
Tempest Minerals Limited undertakes no obligation to update any forward-looking statement to reflect events
or circumstances after the date of this document (subject to securities exchange disclosure requirements).
The information in this document does not take into account the objectives, financial situation or particular
needs of any person or organisation. Nothing contained in this document constitutes investment, legal, tax or
other advice.
Competent Person Statement
The scientific and technical information contained within this Report is based on, and fairly represents
information prepared by Mr Don Smith, a Competent Person who is a member of AusIMM and the Australian
Institute of Geoscientists (AIG).
Mr Smith is the Managing Director of the Company and has sufficient experience that is relevant to the style
of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as
a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration
Results, Mineral Resource and Ore Reserves”. Mr Smith consents to the inclusion in this report of the matters
based on his information in the form and context in which it appears.
Information relating to Previous Disclosure
This report contains information extracted from previous ASX market announcements reported in accordance
with the 2012 JORC Code and is available for viewing at www.tempestminerals.com.
The information in this report that relates to exploration results and exploration targets as reported above were
last reported by the Company in compliance with the 2012 Edition of the JORC Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves. The Company confirms that it is not
aware of any new information or data that materially affects the information included in the market
announcements referred to above and further confirms that all material assumptions and technical
parameters underpinning the exploration results and exploration target contained in those market releases
continue to apply and have not materially changed.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
3 | P a g e
Compliance Statement
The information in this operations report that relates to the Mineral Resource for the Remorse Project are
extracted from the ASX Announcement listed below which is available on the Company website at
www.tempestminerals.com and the ASX website ( ASX code: TEM):
Date Announcement
8 May 2025 Inaugural JORC Mineral Resource - Remorse Project - Amended
The Company confirms that it is not aware of any new information or data that materially affects the
information included in the original market announcements and that all material assumptions and technical
parameters underpinning the estimates in the market announcements continue to apply and have not
materially changed. The Company confirms that the form and context in which the Competent Person’s
findings are presented have not been materially modified from the original market announcement.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
4 | P a g e
Corporate Information
Directors and Company Secretary
Brian Moller (Non-executive Chairman)
Don Smith (Managing Director)
Andrew Haythorpe (Non-executive Director)
Owen Burchell (Non-executive Director)
Mr Paul Jurman (Company Secretary)
Head Office and Registered Office
Tempest Minerals Limited
Level 2, Suite 9
389 Oxford Street
Mt Hawthorn, WA 6016
Tel: +61 8 9200 0435
www.tempestminerals.com
Auditors
HLB Mann Judd
Level 4, 130 Stirling Street
Perth WA 6000
Share Registry
Automic Pty Ltd
Level 5, 126 Philip Street
Sydney NSW 2000
Tel: 1300 288 664
www.automicgroup.com.au
Stock Exchange Listing
Australian Securities Exchange Ltd
ASX Code: TEM
Solicitor
Hopgood Ganim Lawyers
Level 10, 360 Queen Street
Brisbane QLD 4000
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
5 | P a g e
Directors’ Report
The directors submit their report on the consolidated entity (“Group”) consisting of Tempest Minerals Limited
(“Company”, “Tempest” or “TEM”) and the entities it controlled at the end of, and during, the half-year ended
31 December 2025.
Directors
The following persons were Directors of the Company at all times during and since the end of the financial
period:
- Brian Moller
- Don Smith
- Andrew Haythorpe
- Owen Burchell
Results
The Group’s operating loss for the financial period, after applicable income tax was $3,930,368 (2024:
$419,233).
Review of Operations
During the period, the Company’s principal activity was mineral exploration and identification of new
exploration opportunities.
Projects
Figure 1: TEM Projects
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
6 | P a g e
Yalgoo
The Company’s prior holding in the Yalgoo region of Western Australia totalled approximately 1,000 km2
located near a number of high-profile neighbours and prospective for multiple commodities.
Figure 2: Yalgoo Projects Overview
Tempest previously used data-driven processes to identify poorly or unexplored areas of highly prospective
geology. This approach has had considerable success and includes the discovery of multiple instances of
new mineralisation including the substantial Remorse magnetite deposit in 2024.
During the reporting period, TEM identified further iron mineralisation, signed an option agreement with Green
Iron and Steel (GISA) and signed a binding agreement with Capricorn Metals Limited (CMM) for CMM to
acquire the greater Yalgoo Project tenement package. This was completed in February 2026.
Remorse Deposit
The Remorse Deposit is located on the eastern side of the Yalgoo Project. In September 2024 exploration
drilling for base metals ultimately resulted in the discovery of a large-scale magnetite iron deposit. Tempest
has outlined an exploration target, completed an initial mineral resource estimate, completed metallurgical
studies and commenced collaboration under an MOU with prospective Mid-West GreenSteel developer
Green Steel and Iron Pty Ltd (GISA) who intend to build a large-scale multi-user iron processing hub nearby.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
7 | P a g e
Figure 3: Regional infrastructure, Remorse Deposit and potential GreenSteel site
Table 1: Mineral Resource Estimate for the Remorse Iron Deposit reported at 28% Fe cut-off grade.
Classification
Mass
Mt
Volume
thousand m3
Density
t/m3
Average Value
Fe%
Inferred 63.5 16 900 3.76 30.6
Total 63.5 16 900 3.76 30.6
Halo Target
In response to the Remorse magnetite iron deposit discovery in 2024 - TEM conducted a data review for similar
geology nearby and this indicated the likely presence of further iron mineralisation at the Halo Target.
Halo is located ~5km west of the Remorse Deposit. Results from historical work done by a number of previous
explorers include rock chip results up to 58% Fe and 62% Fe.
Tempest also completed mapping at the Halo Target and identified at least five parallel iron formation units
with similar characteristics to the Remorse Deposit. However, the Halo Target appears to be multiple times
larger and can traced for at least 10 km.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
8 | P a g e
Figure 4: Yalgoo Project - Remorse Iron Deposit and Halo Iron Target
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
9 | P a g e
Figure 5: Halo Iron Target with magnetics (TMI) and legacy rock chip sampling (digitised).
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
10 | P a g e
GISA Agreement
The collaboration MOU with GISA was further deepened by the two parties with TEM entering into a
conditional binding agreement.
The Option Agreement includes TEM granting GISA an option to acquire its Remorse Magnetite Project and
as part of its consideration, will be entitled to 50% of the issued capital of GISA. TEM will also receive options.
GISA is planning to progress the proposed establishment and development of a green iron and steel
production facility in the Yalgoo region with a view to ultimately carrying out an initial public offering and
stock exchange listing (IPO).
Capricorn Agreement
TEM and Capricorn Metals Ltd (CMM) entered into a binding agreement for CMM to acquire the Yalgoo
Project for a total consideration of $4.5 million (Agreement).
The deal terms were as follows:
an initial cash deposit of $100,000 (paid);
$400,000 cash on completion; and
$4,000,000 by way of the issue of fully paid ordinary shares in CMM to TEM, calculated by reference to
the 5-day VWAP prior to completion.
The Agreement covers the tenure of the Yalgoo Project, with the key transaction terms including:
Tenements comprising the Yalgoo Project will be transferred in full to CMM free of any third-party
commitments or royalties;
TEM retains ownership of the eastern tenements recently identified as bearing iron mineralisation;
TEM granted CMM exploration and development rights in respect of all minerals other than iron ore
on the Iron Tenements; and
CMM has agreed to make discovery or production-based milestone payments payable once per
tenement, as follows:
o $750,000 in cash upon the announcement by CMM of a JORC compliant Mineral Resource
Estimate in excess of 75,000 ounces of gold on the Yalgoo Project;
o $750,000 in cash upon the announcement by CMM of a board decision to commence a
commercial mining operation on the Yalgoo Project;
The Agreement was completed in February 2026 and Tempest received $400,000 and $4,000,000 worth of
CMM shares.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
11 | P a g e
Mount Magnet
Mt Magnet is a prolific multi-million ounce gold mining centre with numerous large scale, long life open pit
and underground mines currently in operation. It has been operated by major resources companies such as
Western Mining Corporation and Harmony Gold Ltd as well as more contemporary successful mid-tier
companies such as Ramelius Resources Ltd and Westgold Ltd.
Figure 6: Overview of Mt Magnet and the Range Project
Range Project
Located in the heart of the Mount Magnet mineral field and 5km along strike of the prolific +6Moz Mount
Magnet Operations, the Range Project consists of 17 tenements for 20km2. During the reporting period, TEM’s
primary focus was on work in Mt Magnet with a range of exploration activities conducted.
Tempest engaged consultants who assisted in geological mapping and interpretation and
stratigraphic re-interpretation resulting in enhanced understanding of the geology, potential
mineralisation controls, and a new geology interpretation better aligned with the context of the
adjacent Mount Magnet and Boogardie Basin geology;
Further internal geological mapping using this base work with respect to stratigraphy and alteration
resulted in further identified targets;
Rock chip sampling with several results up to 1g/t gold with sulphide and siderite alteration over a
strike length of ~1km contained in fractured quartz veins similar to the nearby Britannia Well open pit
mineralisation and Boogardie Break mineralisation in the Mount Magnet region;
A broad auger geochemical sampling program covering the western side of the project is anticipated
to potentially extend known targets at the project in addition to generating new targets.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
12 | P a g e
Completion of an inaugural 19 hole 1,500m Reverse Circulation Drilling program for the Range
Project. The program tested multiple targets including testing the nearby potential extension of the
Britannia Well open pit.
Drilling identified consistent gold results over 1.5km strike length. Drill intercepts include: 3m @ 3.2g/t Au from
58m (including 1m@5.9g/t), 3m@1.9g/t gold from 13m and 2m@1.2g/t Au from 21m. These shallow gold results
lie adjacent to existing open pits and less than 10km from the planned Ramelius Resources (ASX:RMS) major
processing circuit expansion 17 .
Figure 7: Range Project upcoming Auger (Yellow) and RC Drilling (Green)
Figure 8: Long Section of Range Project with Brittania Pit (left) and intercepts >0.1g/t Au (TEM symbols)
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
13 | P a g e
Five Wheels
The Five Wheels Project is 266km2 of granted tenure in
the Earaheedy region of Western Australia proximal to
the high-profile world-class Rumble Resources Ltd
(ASX:RTR) discoveries. The project remains largely
under-explored (or unexplored for base metals) and
shares similar geology to both the nearby Rumble
Resources Chinook deposit and the emerging
Strickland Metals Ltd (ASX:STR) zinc-lead-copper
discoveries.
The Project is located in the Earaheedy Basin where a
major geological unconformity surrounding the edge
of the basin hosts the initial Rumble Resources
discoveries. More recent exploration implies that
multiple key geological sequences are or have the
potential to be mineralised and the prospectivity is
more widespread than originally considered.
Figure 9: Five Wheels Project Location
Figure 10: Five Wheels Simplified Project Geology Map With RTR Project (original red - current blue)
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
14 | P a g e
Elephant Project
The Elephant Project comprises 194km2 (135km2 granted - 59km2 application) of highly prospective exploration
leases. The location on the edge of a geological block with (the suture between the Yilgarn and Albany-
Fraser) is a favourable location for major discoveries as evidenced by the presence of multiple world class
deposits in similar environments along this trend.
The project was pegged primarily due to a strong geophysical anomaly and coincident geochemical data
from nearby previous exploration. The large scale and nature of the anomaly bear similarities to other world
class deposits in the regions such as Tropicana of which Tropicana peak soil was 31pbb with 0-15m cover while
the Elephant Target is 5-10pbb with 100-150m of cover.
Figure 11: Elephant Project Location and regional exploration context
Elephant Project
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
15 | P a g e
International Exposure
In addition to the Company’s Australian focussed assets, Tempest maintains exposure through strategic
positions in a number of international projects.
Africa
Through a divestment deal in 2020, Tempest retains a sizable holding (25 million shares)
in London listed Premier African Minerals (AIM:PREM). PREM have significant market
upside through development of their portfolio.
USA
Argosy Minerals Ltd (ASX:AGY) are progressing their Tonopah Lithium Project (TLP)
located in a world class mining jurisdiction of Nevada, United States of America.
Tempest retains an interest in the project through a A$250,000 milestone based cash
payment entitlement.
Growth
Tempest continues to actively investigate and evaluate new growth opportunities in a number of jurisdictions
and commodities that may bring added value to Tempest shareholders.
Corporate
Subsequent Events
In February 2026, the Company advised the completion of the transaction with Capricorn Metals Limited
(CMM) for the disposal of the Yalgoo Project for a total consideration of $4.5 million with further milestone
payments possible upon future discoveries or production. Tempest will retain the iron rights for the previously
identified iron bearing tenements which host the Remorse Deposit and Halo Targets.
In March 2026, Tempest announced it had entered into a conditional agreement (Agreement) to acquire
Zealandia Resources Pty Ltd (Zealandia), owner of four advanced gold projects covering 145 km² in New
Zealand’s North Island, strategically located within the Taupo Volcanic Zone and the Hauraki Goldfields.
The material terms of the Agreement are as follows:
1. Subject to the satisfaction or waiver of certain conditions precedent, Tempest will acquire all of the
shares in Zealandia from the Key Vendors and all other shareholders (Acquisition);
2. As consideration for the Acquisition, Tempest agrees to pay the shareholders of Zealandia (Vendors)
$2M by the issue of Tempest shares at an issue price being the 10-day VWAP for Tempest shares prior
to the announcement of entry into the transaction documentation required. (Acquisition Shares);
3. Tempest has also agreed to pay the Vendors on a staged basis $2 m of performance shares which
upon the milestones being met within 5 years of completion, are convertible into ordinary shares in
Tempest as follows (Performance Shares):
i. $500,000 of the Performance Shares will convert upon the obtainment in any drilling
program of an intersection of equal or greater than 10 gram-metres Au (or calculated
/ metal equivalent);
ii. $500,000 of the Performance Shares will convert upon the obtainment in any drilling
program of an intersection of equal or greater than 20 gram-metres Au (or calculated
/ metal equivalent);
iii. $500,000 of the Performance Shares will convert upon the obtainment of an Inferred
(or higher classified) JORC resource of at least 200,000 ounces Au at an average
grade of at least 2 g/t Au (or calculated / metal equivalent); and
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
16 | P a g e
iv. $500,000 of the Performance Shares will convert upon the obtainment of an Inferred
(or higher classified) JORC resource (in compliance with the JORC Code edition then
mandated by the ASX Listing Rules) of at least 500,000 ounces Au at an average grade
of at least 4 g/t Au (or calculated / metal equivalent).
There are a number of conditions precedent required to be satisfied before Completion, including shareholder
approval of the transaction, which is planned to be held in Q2 2026.
There were no other material matters or circumstances that have arisen since the end of the reporting date
which significantly affected or may significantly affect the operations of the Group, the results of those
operations, or the state of affairs of the Group that required disclosure in this financial report.
Auditor’s Independence Declaration
The auditor’s independence declaration under section 307C of the Corporations Act 2001 is included in this
financial report.
Signed in accordance with a resolution of the Board of Directors.
Don Smith
Managing Director
12 March 2026
Perth, WA
AUDITOR’S INDEPENDENCE DECLARATION
As lead auditor for the review of the consolidated financial report of Tempest Minerals Limited for
the half-year ended 31 December 2025, I declare that to the best of my knowledge and belief, there
have been no contraventions of:
a) the auditor independence requirements of the Corporations Act 2001 in relation to the review;
and
b) any applicable code of professional conduct in relation to the review.
Perth, Western Australia
12 March 2026
M R Ohm
Partner
17
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
18 | P a g e
Consolidated Statement of Profit or Loss and Other Comprehensive Income
for the Half-Year Ended 31 December 2025
Note 31 Dec 2025 31 Dec 2024
$ $
Interest received 21,423 15,096
Corporate and administrative expenses 2 (335,610) (321,133)
Depreciation (1,841) (3,587)
Employee benefits expense 2 (163,329) (155,813)
Exploration expenses written off / impaired 3 (3,276,749) (110,275)
Foreign exchange gain/(loss) (3,977) 918
Impairment on loans provided (10,465) -
Legal expenses (33,439) (29,838)
Share-based payments expense 9 (121,504) -
Fair value gain on financial assets at FVTPL 11 (4,877) 185,399
Loss before income tax expense (3,930,368) (419,233)
Income tax expense - -
Loss for the period (3,930,368) (419,233)
Other comprehensive income - -
Total comprehensive loss for the period (3,930,368) (419,233)
Loss for the period attributable to:
Owners of the parent company (3,927,893) (419,114)
Non-controlling interests (2,475) (119)
(3,930,368) (419,233)
Total comprehensive loss for the period attributable to:
Owners of the parent company (3,927,893) (419,114)
Non-controlling interests (2,475) (119)
(3,930,368) (419,233)
Loss per share attributable to owners of the parent company Cents Cents
Basic and diluted loss per share (0.61) (0.07)
The accompanying notes form part of these financial statements.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
19 | P a g e
Consolidated Statement of Financial Position
as at 31 December 2025
Note 31 Dec 2025 30 June 2025
$ $
CURRENT ASSETS
Cash and cash equivalents 659,238 1,782,549
Trade and other receivables 51,179 55,448
Prepayments 104,619 76,779
Financial assets at fair value through profit or loss (FVTPL) 11 1,611 6,805
Assets held for Sale – Yalgoo tenements 12 4,500,000 -
Total Current Assets 5,316,647 1,921,581
NON-CURRENT ASSETS
Plant and equipment 3,898 5,739
Exploration and evaluation assets 3 2,747,650 9,915,371
Total Non-Current Assets 2,751,548 9,921,110
TOTAL ASSETS 8,068,195 11,842,691
CURRENT LIABILITIES
Trade and other payables 4 324,657 391,088
Other Liabilities – Deposits held 4 100,000 -
Total Current Liabilities 424,657 391,088
TOTAL LIABILITIES 424,657 391,088
NET ASSETS 7,643,538 11,451,603
EQUITY
Issued capital 9 25,903,343 25,902,544
Reserves 225,907 104,403
Accumulated losses (18,449,647) (14,521,754)
Equity attributable to owners of the parent company 7,679,603 11,485,193
Non-controlling interests (36,065) (33,590)
TOTAL EQUITY 7,643,538 11,451,603
The accompanying notes form part of these financial statements.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
20 | P a g e
Consolidated Statement of Changes in Equity
for the Half-Year Ended 31 December 2025
Attributable to Owners of Parent Company
Note Issued Capital
Accumulated
Losses
Share-Based
Payments
Reserve
Total
Non-
controlling
Interests
Total Equity
$ $ $ $ $ $
Balance at 1 July 2024 23,488,074 (13,184,501) 196,305 10,499,878 (1,069) 10,498,809
Derecognition of outside equity interest due to
deregistration
- (1,104) - (1,104) 1,104 -
Loss for the period - (419,114) - (419,114) (119) (419,233)
Other comprehensive income - - - - - -
Total comprehensive loss - (420,218) - (420,218) 985 (419,233)
Issue of options - - 50,489 50,489 - 50,489
Issue of shares 932,291 - - 932,291 - 932,291
Share issue costs (113,765) - - (113,765) - (113,765)
Balance at 31 December 2024 24,306,600 (13,604,719) 246,794 10,948,675 (84) 10,948,591
Balance at 1 July 2025 25,902,544 (14,521,754) 104,403 11,485,193 (33,590) 11,451,603
Loss for the period - (3,927,893) - (3,927,893) (2,475) (3,930,368)
Other comprehensive income - - - - - -
Total comprehensive loss - (3,927,893) - (3,927,893) (2,475) (3,930,368)
Issue of options 9 - - 121,504 121,504 - 121,504
Issue of shares 9 813 - - 813 - 813
Share issue costs 9 (14) - - (14) - (14)
Balance at 31 December 2025 25,903,343 (18,449,647) 225,907 7,679,603 (36,065) 7,643,538
The accompanying notes form part of these financial statements.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
21 | P a g e
Consolidated Statement of Cash Flows
for the Half-Year Ended 31 December 2025
31 Dec 2025 31 Dec 2024
$ $
CASH FLOWS FROM OPERATING ACTIVITIES
Interest received 7,245 15,096
Payments to suppliers and employees (683,862) (644,802)
Net cash used in operating activities (676,617) (629,706)
CASH FLOWS FROM INVESTING ACTIVITIES
Payments for exploration and evaluation assets (576,516) (1,487,544)
Payments for purchase of Plant and Equipment - (9,131)
Deposit received from sale of tenements – including
GST
110,000 202,208
Receipts from R & D tax refund 96,315 253,914
Net cash used in investing activities (370,201) (1,040,553)
CASH FLOWS FROM FINANCING ACTIVITIES
Proceeds from issue of securities 813 830,702
Share issue costs (77,306) (83,664)
Net cash (used in) / provided by financing activities (76,493) 747,038
Net decrease in cash held (1,123,311) (923,221)
Cash at beginning of period 1,782,549 1,465,655
Foreign exchange movement on cash balances - 2
Cash at End of Period 659,238 542,436
The accompanying notes form part of these financial statements.
TEMPEST MINERALS LIMITED – ACN 612 008 358 INTERIM FINANCIAL REPORT 2025
22 | P a g e
Notes to the Financial Statements
for the Half -Year Ended 31 December 2025
NOTE 1: SUMMARY OF MATERIAL ACCOUNTING POLICIES
Basis of Preparation
These general purpose financial statements for the interim half-year reporting period ended 31 December
2025 have been prepared in accordance with the Corporations Act 2001 and Australian Accounting
Standard AASB 134 "Interim Financial Reporting". Compliance with AASB 134 ensures compliance with IAS 34
“Interim Financial Reporting”. The historical cost basis has been used, except for financial assets at fair value
and the valuation of share based payments. For the purpose of preparing the half-year financial report, the
half-year has been treated as a discrete reporting period.
This interim financial report does not include all notes of the type normally included in the Annual Report.
Accordingly, this report is to be read in conjunction with the Annual Report of Tempest Minerals Limited for the
year ended 30 June 2025, together with any public announcements made during the half-year.
Significant accounting judgments and key estimates
The preparation of half-year financial reports requires management to make judgments, estimates and
assumptions that affect the application of accounting policies and the reported amounts of assets, liabilities,
income and expenses. Actual results may differ from these estimates.
In preparing this half-year report, the significant judgments made by management in applying the Group’s
accounting policies and the key sources of estimation uncertainty were the same as those that applied to the
Group when compiling its annual 30 June 2025 financial statements.
The same accounting policies and methods of computation have generally been followed in these half-year
financial statements as compared with the corresponding half-year financial statements and the most recent
annual financial statements except for the adoption of new and amended standards as set out below.
Going Concern
The financial statements have been prepared on a going concern basis which contemplates the continuity
of normal business activities and the realisation of assets and discharge of liabilities in the ordinary course of
business.
Management has prepared a detailed cash flow forecast for the next 12 months from the date of this report,
and the directors are satisfied that the going concern basis of preparation is appropriate.
During the period, Tempest announced a binding agreement with Capricorn Metals Limited (CMM) for CMM
to acquire the greater Yalgoo Project tenement package for consideration of $4.5 million with further
milestone payments to be made upon further discoveries or production within the tenement package.
The consideration comprised:
● an initial cash deposit of $100,000 (paid in December 2025 - refer Note 4);
● $400,000 cash on completion; and
● $4,000,000 by way of the issue of fully paid ordinary shares in CMM to Tempest, calculated by
reference to the 5-day VWAP prior to completion.
Completion of the transaction occurre
Share your feedback