JUNE 2017 QUARTERLY REPORT
HIGHLIGHTS:
•
SRK has completed a technical review of the Tonopah Lithium Project
•
Tonopah exploration program has commenced
•
8 WA Exploration Licenses granted in June 2017: hard rock lithium potential
•
WA hard rock lithium exploration program will commence in August 2017
•
SRK has completed a technical review of the Botswana Project
•
Botswana shallow pit sampling program will commence in August 2017
•
New WA Exploration License Applications: cover extensions of target pegmatite bodies outside of
our existing granted Exploration Licenses
Lithium Consolidated Mineral Exploration Limited (ASX: LI3) (“Lithium Consolidated” or the
“Company”) is pleased to report on activities during the June quarter, including the advancement of our
exploration projects.
The Company is now in position to commence significant exploration activities across our key projects in
Nevada, Western Australia and Botswana.
PROJECTS
1. Nevada, USA
Lithium Consolidated is the largest land holder for lithium brine exploration in Nevada, USA.
Lithium Consolidated holds a total of 2,026 placer claims covering 40,480 acres in Nevada in the South Big
Smoky Valley and Teels Marsh basins.
The targeted lithium brine reservoirs of the South Big Smoky Valley and Teels Marsh basins remain
unexploited and underexplored, while the Clayton Valley basin reservoirs to the south have produced lithium
brine for +50 years.
The Tonopah Lithium Project (“TLP”) and Teels Project (“Teels”) have multiple lithium brine reservoir targets
for exploration.
SRK Consulting (U.S.), Inc. (“SRK”) has completed a technical review of the Nevada projects. This technical
review resulted in a positive validation of the lithium brine resource potential at our Nevada projects and the
prioritisation of lithium brine reservoir targets for exploration.
The southern part of TLP has been selected by SRK and the Company as the highest priority area for
exploration given its proximity to the Silver Peak lithium brine mine, which has been in production for +50
years.
The Nevada Division of Water Resources and other sources have indicated that groundwater flows into the
Clayton Valley in part from the Big Smokey Valley. This would indicate both a geological and hydrological
relationship between the southern part of TLP and the Silver Peak lithium brine mine.
LITHIUM CONSOLIDATED MINERAL EXPLORATION LTD ACN 612 008 358
Phone: +61 7 3212 6299 Fax: +61 7 3212 6250 Address: Level 10, 110 Mary Street, Brisbane Q 4000
The Tonopah exploration program over the southern part of TLP will be further defined through the current
geophysical program.
Tonopah Lithium Project (80% ownership interest)
TLP consists of 1,241 placer claims, covering a total area of 24,459 acres in the Big Smokey Valley, where
the south end of TLP is less than 2 miles (3.2km) from Albemarle’s Silver Peak lithium mine, which is North
America’s only producing lithium brine and located in the Clayton Valley.
The Tonopah exploration program is being managed by two high calibre, Nevada based technical consultants.
E. Max Baker is managing the overall exploration program and Bob Ellis is managing the geophysical program.
The Tonopah exploration program has commenced with an initial stage of additional geophysical surveys:
gravity infill acquisition, merge with previous data, 3D density inversion modeling, and interpretation;
a magnetotellurics (“MT”) survey; and
2D seismic surveys located based on the reprocessed gravity data and MT survey results.
Figure 1 shows the additional geophysical survey lines.
MWH Geo-Surveys Ltd. is carrying out a gravity survey over the southern part of the Tonopah Lithium Project.
Bob Ellis is supervising this survey and will merge the data from this survey with existing gravity data to develop
a more complete and higher resolution gravity image of the southern part of TLP.
Zonge International has been selected as the preferred contractor for the MT survey and will commence the
MT survey in October 2017.
Our maiden drilling program in Nevada will follow the MT survey and commence in the fourth quarter of 2017.
Figure 1: Location of Geophysical Survey Lines
Note: Both the MT and the 2D seismic surveys will be along the same lines. Source: SRK
page 2
Teels Project (80% ownership interest)
The Teels Project consists of 785 placer claims, covering 16,021 acres in the Teels Marsh Basin in Mineral
County, Nevada.
The gravity survey data shows that our Teels Project is in a terminal basin with evaporation appearing to be
the only exit path for water in the basin, which may cause the water to become concentrated with dissolved
minerals to form a brine solution.
Our Teels Project claims encircle the claims held by TSXV listed Dajin Resources Corp. (“Dajin”), over the
main Teels Marsh basin and also over another sub-basin immediately south of the main Teels Marsh basin.
Figure 2: Location of the Teels Project in relation to Dajin’s claims
Source: Internal Company Data
2. Australia
Yilgarn Projects (Western Australia) (100% ownership interest)
Lithium Consolidated was granted 8 Exploration Licences (“ELs”) by the Western Australia Department of
Mines and Petroleum, in June 2017. These ELs cover 367km² of known lithium-fertile “belts” undercover in the
Yilgarn Craton in Western Australia and have potential for hard-rock lithium mineralisation.
Lithium Consolidated has executed an Agreement for Heritage Protection Over Mining Tenure with the Ngadju
Native Title Aboriginal Corporation RNTBC for the ELs.
The remaining 2 Exploration License Applications overlap conservation reserves and have been referred to
the Department of Parks and Wildlife for the Minister’s comment and recommendation and cannot be granted
until that process is finalised.
The WA hard rock lithium exploration program will commence in August 2017.
New Exploration License Applications
Lithium Consolidated applied for E 63/1862 (“Ten Mile South”) and E 15/1616 (“Wanoc”) Exploration Licenses,
in July 2017.
page 3
These new Exploration License Applications will expand our presence over target pegmatite bodies which
extend outside of our existing granted ELs.
Figure 3: Western Australia ELs and ELAs location
Eucla Projects (South Australia) (100% ownership interest)
Lithium Consolidated has 5 Exploration License Applications (“ELA”) covering 5,680 km2 of the Eucla Basin in
South Australia.
The Company is seeking the grant of these ELAs, subject to the requirements of the Native Title Act 1993
(Cth) (NTA). The Maralinga Tjarutja people hold native title rights over these ELAs.
Lithium Consolidated plans to commence exploration activities upon the grant of these ELAs.
3. Botswana (80% ownership interest)
Lithium Consolidated has 6 Prospecting Licences and 2 Prospecting License Applications in the Makgadikgadi
Pans in north eastern Botswana.
The Makgadikgadi Basin is a large area of low relief. The Sua Pan and Ntwetwe Pan that make up the
depocenter of the greater Makgadikgadi Basin have the lowest elevation in the Kalahari at 890 metres above
sea level, making it the final collection point for all the rivers and streams in the basin.
The regional and local geology indicate a potential for a mineral rich brine in the Makgadikgadi Pans area.
Lithium concentration results from the only available brine samples are on the northern edge of the Sua Pan
and range from negligible levels to 224mg/L of Li.
SRK has completed a technical review of the Botswana project and has recommended an initial shallow pit
sampling program for further investigation of the lithium brine resource potential at the Botswana project.
page 4
This shallow pit sampling program will give a ‘top of brine’ geochemical signature to define areas of interest
for initial drilling and a deeper sampling program.
The Botswana shallow pit sampling program will commence in August 2017
Overlapping Prospecting Licences
The Department of Mines in Botswana (the “Department”) have cancelled portions of Prospecting Licenses
267/2016 and 268/2016 due to what the Department have advised is the Department’s mistake in issuing the
same ground for the same mineral commodity to another company.
This cancellation only affects 2 of the 6 Prospecting Licences and a small part of the original Prospecting
License area of 5680km2.
Figure 4: Sampling Program Pit Locations (shown as ‘red areas’ on the map)
Source: SRK
CORPORATE
The Company continues to review corporate development opportunities as they arise.
Details of the Company’s financial activities during the quarter are set out in the Appendix 5B cash flow report.
Capital structure
At the end of the quarter, there were 89,972,122 fully paid ordinary Shares, 4.0 million unlisted Options and
7.5 million unlisted Performance Rights on issue.
page 5
For more information, please contact:
Duncan Cornish
Company Secretary
Phone: +61 7 3212 6299
Email: investors@lithiumconsolidated.com
Please visit us at: www.lithiumconsolidated.com
CAUTIONARY STATEMENTS
Forward-looking statements
This document may contain certain forward-looking statements. Such statements are only predictions, based
on certain assumptions and involve known and unknown risks, uncertainties and other factors, many of which
are beyond the company’s control. Actual events or results may differ materially from the events or results
expected or implied in any forward-looking statement.
The inclusion of such statements should not be regarded as a representation, warranty or prediction with
respect to the accuracy of the underlying assumptions or that any forward-looking statements will be or are
likely to be fulfilled. Lithium Consolidated undertakes no obligation to update any forward-looking statement to
reflect events or circumstances after the date of this document (subject to securities exchange disclosure
requirements).
The information in this document does not take into account the objectives, financial situation or particular
needs of any person or organisation. Nothing contained in this document constitutes investment, legal, tax or
other advice.
page 6
Exploration Tenements
Lithium Consolidated held the following interests in claims and tenements at the end of the quarter:
Project Name
Number of Claims
Lithium Consolidated
Interest
Location of
Claims
Tonopah Lithium Project (“TLP”)
1,241
80%
Nevada, USA
Teels March (“Teels”)
785
80%
Nevada, USA
Tenement Number
Lithium Consolidated
Interest
Location of Tenements
Bedonia
E 6301814
100%
Western Australia
Caranning
E 6301815
100%
Western Australia
Windarling
E 7702384
100%
Western Australia
Esmond
E 6903455
100%
Western Australia
Junction
E 2802631
100%
Western Australia
Snomys
E 2802632
100%
Western Australia
Ten Mile
E 6301813
100%
Western Australia
Nawoc
E 1501542
100%
Western Australia
Cool
E 2802651
100%
Western Australia
Dundas
E 6301826
100%
Western Australia
Ten Mile South
E 631862
100%
Western Australia
Wanoc
E 151616
100%
Western Australia
Lake Dey Dey
2016/00127
100%
South Australia
Lake Maurice
2016/00128
100%
South Australia
Nurrari
2016/00129
100%
South Australia
Wyola North
2016/00130
100%
South Australia
Wyola South
2016/00131
100%
South Australia
-
263/2016
80%
Botswana
-
264/2016
80%
Botswana
-
265/2016
80%
Botswana
-
266/2016
80%
Botswana
-
267/2016
80%
Botswana
-
268/2016
80%
Botswana
-
269/2016
80%
Botswana
270/2016
80%
Botswana
Tenement Name
Yilgarn Project
Eucla Basin Project
Botswana Project
page 7